How long does it take to implement an AMR system?

AMR & Intralogistics
AMRImplementationProject PlanningIntegrationWMS

Implementation duration depends on complexity:

Typical Project Phases:

  1. Consulting & Planning (2-4 weeks):

    • Analysis of current processes and requirements
    • Selection of AMR models and fleet size
    • ROI calculation and project planning
  2. Mapping & Configuration (1-2 weeks):

    • Creation of digital environment map
    • Definition of routes, pick-up, and drop-off zones
    • Traffic rule configuration
  3. Integration (2-6 weeks):

    • Connection to WMS/ERP system
    • API integration for order handoff
    • Fleet management setup
  4. Testing & Optimization (2-4 weeks):

    • Parallel operation with existing processes
    • Route optimization and fine-tuning
    • Staff training

Total Duration:

  • Simple setup (1-3 AMRs, no WMS integration): 4-6 weeks
  • Medium project (5-10 AMRs, WMS integration): 8-14 weeks
  • Large project (10+ AMRs, full ERP integration): 3-6 months

Use the Botomix Robot Finder for an initial needs assessment.